BHILAI STEEL PLANT, FROM INDIA, EXPANSION DELAYED BY 15 MONTHS

Even as the Steel Ministry races to complete Rs 61,870-crore modernisation and expansion, the process at Bhilai Steel plant (BSP), the largest facility of the state-run giant, has been delayed by 15 months. 

BSP's modernisation and expansion plan, which entails an investment of Rs 17,266 crore, raising steel capacity from 3.93 million tonnes per annum (MTPA) to 7 MTPA, has been delayed as SAIL had to terminate contracts twice due to "unsatisfactory performance .. 